Construction Progress

01 May 2026

Plastering works in stairwells and common areas of the building are in the final stage.
In the apartments, wall tiling in bathrooms has been completed, and the installation of suspended ceilings in these areas is nearing completion.
In addition, plumbing and sanitary installations in the bathrooms are in the final stage, leaving these areas prepared for the subsequent installation of sanitary fixtures.
Terrace flooring works have also been carried out, with final finishing works currently in progress.